Connection tariffs

Permenergo

Since January 01, 2011 Decree #97-e dd. 28.12.2010 new connection fees were approved.

    Basic connection fee, RUR/kW (excl. VAT)
Voltage class Connected capacity Supply reliability category
    I category II category III category
  Over 15 up to 30 kW inclusive 9 812 12 755 14 226
Low voltage (0.4 kV) Over 30 kW up to 100 kW inclusive 9 812 12 755 14 226
  Over 100 kW up to 750 kW inclusive 10 338 13 438 14 990
Average Up to 100 kW inclusive 9 606 12 487 13 928
voltage II (6-10 kV) Over 100 kW up to 750 kW inclusive 9 000 11 700 13 050

For calculation of connection price the following multipliers are added to the basic connection fee:

Permenergo Multiplier
Perm municipal grids 1,31
Central grids: the Perm and Dobryanka districts 1,25
Central grids: other districts 0,6
Berezniki grids, Kungur grids, Ocher grids, North grids, Chaikovsky grids, Chusovoy grids 0,6

Sverdlovenergo

In 2011 connection fee approved by RES SO Decree #161-PK dd. 15.12.2010 was as follows:

  Connection fee, RUR/kW (excl. VAT)
Connected capacity, kW Tariff group
  Group 1 and 2 Group 3
over 15 up to 100 3 793 1 926
over 100 up to 4500 4 585 1 779

These fees are applied for applicants requesting the 3rd category of energy supply. If an applicant requests the 1st or 2nd category, the amount of connection fee is determined according to the approved connection rates per each connection. Applicant’s equipment with maximum capacity over 100 kW to an open main substation (taking into account earlier connections in the point) in the Sverdlovsk region is connected under individual projects.

Chelyabenergo

In 2011 in the Chelyabinsk region we were guided by Decree of Chelyabinsk ETO #52/71 dd. 30.12.2010 stipulating a connection rate only for applicants with capacity up to 15 kW equaling RUR 550 (incl. VAT) per 1 connection. For all other applicants connection fee was determined by individual calculations. Since January 01, 2012 Decree of Chelyabinsk ETO #47/2 dd. 29.12.2011 came into force. It stipulates connection fee only for applicants with capacity up to 15 kW, the fee retains at RUR 550 (incl. VAT).